Regulation status (as of 12 November 2026)
- The regulation is Regulation (EU) 2023/1115 on deforestation-free products. It was amended and its application postponed by Regulation (EU) 2025/2650.
- The main obligations apply from 30 December 2026 for large and medium operators and traders, and from 30 June 2027 for micro and small enterprises.
- The cut-off date for deforestation is 31 December 2020.
Dates and obligations can change again. Check the consolidated text on EUR-Lex and the European Commission's guidance before relying on them.
The three steps of due diligence
| Step in the regulation | What EUDR Farm provides | What stays with the operator |
|---|---|---|
| Information collection | Farmer records and consent; plot boundaries or points with how and when they were captured; commodity and product type with HS code; quantities and purchase dates; crop year and collection period; legality documents and questionnaires; where the produce went next | Supplier information beyond what the supply chain enters; the operator's own records |
| Risk assessment | 21 plot tests, satellite screening against open maps, a person's decision on everything not clearly low, quantity checks against what the plots can grow, and the organisation's legality questionnaires per country | The overall risk assessment, including country risk, the other criteria in the regulation and the operator's conclusion |
| Risk mitigation | Requests for more information, re-mapping, rejection and challenge of plots; grievance and complaint handling; plots that cannot be bought from until cleared; lots that cannot be packed until problems are resolved | Deciding that the remaining risk is negligible, any further mitigation, and the due diligence statement |
Production dates
Every lot carries its crop year and a collection period (first and last day of buying), and every purchase its date and the exact plot version it came from. Purchases can only be dated inside the lot's period. Each plot keeps the date its boundary was mapped. Farmers can also record in the app what grows on each plot, when it was planted and its harvest months; that is shown as the farmer's own statement, not checked. The crop year, period and purchase dates are written into the evidence pack.
Commodities and products
EUDR Farm supports coffee and cocoa. Each lot names a product type with its HS heading:
| Commodity | Product types (HS) |
|---|---|
| Coffee | Green coffee beans (0901 11); green, decaffeinated (0901 12); roasted (0901 21); roasted, decaffeinated (0901 22); husks and skins (0901 90) |
| Cocoa | Cocoa beans (1801); shells, husks and waste (1802); paste or liquor (1803); butter, fat and oil (1804); powder (1805) |
Check the exact CN code and whether a product is in scope against Annex I of the regulation for your shipment.
Lot traceability
- A lot is built from purchases, each tied to one verified plot and the exact version of its boundary. A lot can draw on many plots, and a plot can supply many lots.
- After a lot is marked ready, its movements are recorded as events: transport, warehousing, operations (cleaning, washing, drying, sorting, packing, hulling, milling, roasting, grinding, processing), shipping between countries, splitting, merging and termination.
- Each part of the lot is a numbered parcel. Splitting makes new parcels; merging joins them; an operation that makes a different product gives the output a new product type.
- Quantities are reconciled at every step: an event cannot move more than is left, cannot put out more than went in, and cannot be dated before the previous event. What is bought in a crop year is compared with what the plots can grow (area × the commodity's maximum yield), and anything higher is flagged.
- Every facility or country named in an event must have a completed disclosure statement before the lot is packed.
Legality evidence
For each country and commodity there is a checklist of documents (for example land records or permits) defined by EUDR Farm, plus the organisation's own registration and legality questionnaires covering land use rights, environmental protection, forest rules, third-party rights and free, prior and informed consent, labour and human rights, tax, anti-corruption, trade and customs, and the rights of indigenous peoples. Each farmer can also sign a declaration about land use and labour. Documents are stored with their issue and expiry dates and a SHA-256 fingerprint; missing or expired required documents block the lot. EUDR Farm checks that documents are present, dated and in date; it does not judge whether a document is genuine or legally sufficient. The checklist items are currently samples awaiting legal review.
When a concern is raised
- Raised: by a check, by a reviewer, or by anyone through the concern form (they receive a case reference).
- Investigated: a reviewer can ask the organisation for more information; the organisation answers with text and files. Cases move through received, being looked at and waiting for information.
- Mitigated: the plot is cleared with a written reason, rejected, or sent back to be mapped again; a rejected plot cannot be bought from. Withdrawn consent freezes the farmer's plots.
- Escalated: an organisation can challenge a rejection once with new evidence, and complain about how a case was handled.
- Closed: resolved or dismissed, with the reason kept. Every step is kept in the plot's or case's history.
From evidence pack to the due diligence statement
- The organisation packs a lot. The pack fixes the plots, purchases, movements, documents and screening results at that moment.
- The pack is shared with the operator or trader, who checks it (see the page for EU buyers).
- The operator completes its own risk assessment and concludes on the remaining risk.
- An organisation can ask EUDR Farm to file a due diligence statement with the EU Information System from a packed lot (EUDR web service v3); the organisation confirms the statement is its own, and an EUDR Farm administrator files it. The plots go into the statement from the pack's plot file.
Filing a statement is the operator's act and responsibility; EUDR Farm prepares the data and sends it when asked.
Keeping records
The regulation asks operators and traders to keep due diligence information for five years. In EUDR Farm, boundary versions, check and screening results, review decisions, consent events, evidence packs and the audit log cannot be edited or deleted, and nothing is deleted automatically. When a farmer asks for their data to be deleted, their identifying details are removed but the plot and purchase records stay, because traceability records must be kept (see data protection). A timed retention schedule, with deletion after the retention period ends, is not built yet and needs a legal decision on the period.